2026-0045 Nusantara Nickel Smelter, E-House and LV distribution package
C3Accept

Baselines

A baseline is a frozen set of exact revisions and canonical values. Membership is by identifier and content hash, so a later edit to a member is detectable rather than invisible.

SRS section 9.3 and 9.4, baselines and controlled change

Baselines

2

Frozen

1

Members held

9

Open items at HIGH or above

5

A freeze is refused while any of these remain.

Requirement baseline R1, requirement
Frozen 2026-05-13 02:00 by Rangga Prasetyo. Frozen after the first canonisation pass, against specification revision 01.
approved
KindMemberIdentifierHash at freezeStill current
artifact revisionGSPE-P26045-01-E-SPC-001 Rev 01REV-SPC-0014bf9de308aa7superseded since
requirementSPC 3.1 All assemblies shall be design verified and shall comply witREQ-2026-0045-0001f5f73682de59n/a
requirementSPC 3.2 a The main busbar system shall be rated 400 V, three phase, foREQ-2026-0045-00020dca7d4caf29n/a
requirementSPC 3.2 c Each assembly shall withstand a short circuit of 65 kA for 1REQ-2026-0045-00045512090541dfn/a
canonical factRated operational voltage (Ue) = 400 VFCT-2026-0045-0001f32b75c3eefen/a
canonical factRated short-time withstand current (Icw) = 65 kAFCT-2026-0045-00031977754b17b7n/a
Manufacturing baseline M1, manufacturing
Cannot be frozen while the configuration drift and the busbar rating conflict remain open.
draft
KindMemberIdentifierHash at freezeStill current
artifact revisionGSPE-P26045-01-E-SLD-001 Rev 03REV-SLD-00323ad7b0525aeyes
artifact revisionGSPE-P26045-01-M-GAD-001 Rev 01REV-GAD-0017d633b32abc0yes
configuration snapshotCONF-88231 revision 2SNP-2026-0045-0001d73c9cd5a47cn/a
The requirement baseline here points at specification revision 01 while revision 02 is the issued document. That is not a bug in the data, it is the situation the baseline-to-document checker exists to detect: work was frozen against one revision and the source has moved since.