Pick something that might change and see everything that would have to be re-examined, with the path that made it relevant. The traversal is the same one the database performs with a recursive query.

SRS section 12, change impact analysis

Origin
What is changing.

Canonical attributes

Configured items

Requirements

Engineering objects

Nodes reached

16

Requiring rework

15

Gates re-opened

0

Impact of a change to Rated operational voltage (Ue)
Breadth first from the origin. Depth is how many hops away the node sits.
DepthKindNodeDetailReached because itConsequence
1canonical factRated operational voltage (Ue) = 400Canonical since 2026-05-12T16:00:00.000Zis canonised asrework
1engineering objectMSB-01-Q1Incoming air circuit breakeris carried byrework
1engineering objectMSB-01-BB1Main horizontal busbaris carried byrework
1requirementSPC 3.2 aThe main busbar system shall be rated 400 V, three phase, four wire, 50 Hz.is required byrework
2artifactGSPE-P26045-01-E-SPC-001Technical specification, LV switchgear and controlgear assembliesis required by then citesre-read
2artifactGSPE-P26045-01-E-SLD-001Single line diagram, main switchboard MSB-01is carried by then is depicted onrework
2baselineRequirement baseline R1REQUIREMENT baselineis canonised as then is frozen insiderework
2engineering objectMSB-01-PEMain protective earth baris carried by then earthed torework
2engineering objectMSB-01-Q11Feeder to motor control centre MCC-01is carried by then feedsrework
2engineering objectMSB-01-Q12Feeder to auxiliary distribution board DB-EH-01is carried by then feedsrework
2engineering objectMSB-01-PM1Multifunction power meteris carried by then monitored byrework
3artifact revisionRev 02Clarification round two. Ambient temperature raised to 65 C in clause 3.6.is required by then cites then is currently atrework
3artifact revisionRev 03Incomer protection settings updated after the coordination study.is carried by then is depicted on then is currently atrework
3engineering objectMCC-01-BB1Motor control centre busbaris carried by then feeds then feedsrework
3engineering objectDB-EH-01-BB1Auxiliary board busbaris carried by then feeds then feedsrework
4baselineManufacturing baseline M1MANUFACTURING baselineis carried by then is depicted on then is currently at then is frozen insiderework
The distinction between rework and re-read matters. A change that reaches a frozen baseline or an issued drawing costs money; a change that only reaches an ontology definition costs a read. Reporting both as impact would make the analysis useless.