2026-0045 Nusantara Nickel Smelter, E-House and LV distribution package
C3Accept

Nusantara Nickel Smelter, E-House and LV distribution package

PT Nusantara Nickel Industri, contract NNI-EPC-2026-114, Morowali, Central Sulawesi.

PRJ-2026-0045, created 2026-05-04

approved
Project record
Identifier
PRJ-2026-0045
Project code
2026-0045
Contract
NNI-EPC-2026-114
Project manager
Rangga Prasetyo
Engineering lead
Dewi Anggraini
Site
Morowali, Central Sulawesi

Systems

3

Second level of the hierarchy.

Configured items

3

Each maps to one upstream configuration.

Requirements

12

Extracted, canonised and traced to a source anchor.

Open items

8

Unresolved questions, conflicts and check failures.

Systems
A system groups configured items that are commissioned together.
CodeSystemDisciplineDescriptionItems
01Main LV distributionElectricalMain switchboard, distribution boards and the interconnecting busway.2
02Motor controlElectricalMotor control centres serving the ore handling and dust extraction plant.1
03Control and monitoringInstrumentation and ControlMetering, protection relays and the plant communication interface.0
Configured items
Each item carries a full configuration snapshot with a content hash, so drift is detectable rather than assumed away.
TagNameFamilyConfigurationDriftStatus
MSB-01Main switchboard, 400 VLV_PANELCONF-88231Drift detectedin review
MCC-01Motor control centre, ore handlingLV_PANELCONF-88240In syncdraft
DB-EH-01E-House auxiliary distribution boardLV_PANELCONF-88252In syncdraft
Gate readiness
Evaluated live against the record. A gate is a completion contract at project scope, not a checkbox.
GateNameTracer scopeReady
G1Requirement baselineDeferred3 outstanding
G2Configuration freezeDeferred2 outstanding
G3Design releaseDeferred1 outstanding
G4Manufacturing releaseIn scope6 outstanding
G5FAT releaseIn scope5 outstanding
G6aIntegrated system testDeferred1 outstanding
G6bSite acceptance testDeferred1 outstanding
G7HandoverDeferred1 outstanding
Requirements needing attention
Anything still below L3 cannot support a gate decision.
ReferenceStatementCriticalityTrust
SPC 3.6The design ambient temperature shall be 65 C.HighL1
SPC 3.7The assembly shall provide adequate protection for operating personnel in the event of an internal arcing fault.CriticalL1
The hierarchy shown here is the one the specification fixes in section 5.1. Nothing in this sandbox creates an engineering object outside a configured item, because an object with no configuration behind it cannot be checked against anything.